Why do New Jersey solar quotes run so far apart?
Because the two published averages count different things, and neither is wrong. EnergySage publishes $2.61 per watt as its November 2026 average, and its page does not say which projects the average covers. The BPU's $3.66 per watt is the average reported cost of about 17,000 residential projects that the state's registration manager accepted between July 2025 and March 2026, and the Board used it in its incentive model.
On a 6 kW roof the gap is real money: $16,431 on EnergySage's table against $21,960 at the BPU figure (6,000 watts times $3.66). At the 9.8 kW size the BPU uses as its model home, the state number works out to about $35,900, while EnergySage's 10 kW price is $25,902.
Use the higher figure as the budget and the lower one as the target. If three written quotes on the same panels and inverter all land near $3.60 a watt, the state's number describes your market. If one comes in at $2.80, ask what it leaves out: ground-level conduit runs, a roof reinforcement, a main panel upgrade, or permitting fees. Our quote comparison worksheet lists the line items to match up.
What does SuSI pay, and for how long?
SuSI pays $77 for every megawatt-hour a residential system generates, for 15 years. Each megawatt-hour is one Solar Renewable Energy Certificate (SREC-II), and the BPU's Administratively Determined Incentive (ADI) program sets the dollar value instead of an auction. The May 21, 2026 order cut the residential rate from $85 to $77 for all registrations received on or after July 27, 2026. EnergySage's New Jersey incentives page, updated September 30, 2026, lists the same $77.
The rate follows the registration date, not the install date, so ask your installer which one your quote carries. A project registered before July 27 under an $85 quote keeps that rate. One registered today does not.
The BPU also set the Energy Year 2027 residential block at 300 MW. Registrations opened June 1, 2026 and run until the block fills or June 1, 2027. Residential sign-ups averaged about 5.2 MW a week in Energy Year 2026. At that pace, 52 weeks use roughly 270 MW, so the block should last the year, but a rush ahead of any further cut could change that. The new rate is a 9% cut, close to the automatic 10% reduction that the program rules apply every three years unless the Board acts.
Here is what the incentive pays on a 6 kW system. The National Laboratory of the Rockies' PVWatts calculator, run for the Newark area with a 20 degree roof tilt, south-facing panels, a fixed roof mount and 14% losses, gives 7,833 kWh a year, or 7.83 MWh. That is a first-year illustration, not a guarantee: our guide to estimating production with PVWatts shows how to rerun it for a specific roof.
| Step |
Arithmetic |
Result |
| Year-one certificates |
7,833 kWh divided by 1,000 |
7.83 SREC-IIs |
| Year-one SuSI payment |
7.83 times $77 |
about $603 |
| Fifteen years, flat output |
$603 times 15 |
about $9,047 |
| Fifteen years, output slipping 0.5% a year (our assumption) |
sum of the yearly payments |
about $8,737 |
The BPU's own model project produces 1,280 kWh per kW after 20% total losses. PVWatts gives 1,305 kWh per kW with its default 14% losses, so the two sources agree closely. EnergySage estimates lifetime SuSI savings of $9,000 to $11,500, which brackets the table above.
How does New Jersey net metering pay?
Net metering gives you one credit for each kilowatt-hour you send to the grid, and those credits cancel later purchases. PSE&G's page describes a 12-month contract year that normally starts when the net meter is installed. At the anniversary true-up it values any credits left over at the New Jersey Clean Energy Program market price, which follows hourly PJM wholesale prices, and resets the bank to zero. The page gives no cents-per-kWh figure for that payout, and EnergySage says generation beyond 100% of your annual use is credited at the wholesale rate.
So a system sized to your annual use earns retail value on nearly every kWh. A system that makes far more than you use earns wholesale value on the surplus, which is a fraction of the retail rate. PSE&G says the allowed size is limited to the home's annual electricity needs, and notes that the average residential system in its territory is about 8 kW.
One caution on policy. The BPU's November 2024 stakeholder slides report that net metering capacity passed 5.8% of total kilowatt-hours sold during Energy Year 2024 and that the Board opened a successor-policy proceeding, Docket QO24090723. PSE&G's page still describes the current rules. Before signing, ask the installer whether the contract states which net metering terms apply to your system.
A grid outage shuts the system off unless you add battery backup, which PSE&G says is a safety rule for line workers. The state's planned residential storage incentive, the Garden State Energy Storage Program, had not launched as of EnergySage's September 30 update, and batteries installed before it takes effect will not qualify.