Why does a Virginia system take almost 12 years to pay back?
Because each kilowatt-hour it makes is worth 17.64 cents, against 21.77 cents in Pennsylvania or 24.51 cents in Connecticut (EIA, August 2026). The system costs about the same as in those states. The savings per kWh are lower, so the payback stretches.
The arithmetic on an 8 kW system looks like this. It is an illustration, not a forecast, and it assumes 1,250 kWh of production per kW per year, a typical figure for a south-facing roof in central Virginia. Production for your own roof is a PVWatts run away; our PVWatts guide shows how to do it.
- Production: 8 kW x 1,250 kWh = 10,000 kWh a year
- Value if every kWh offsets retail power: 10,000 x $0.1764 = $1,764 a year
- Payback on $21,025: $21,025 / $1,764 = 11.9 years
That lands within a quarter of a year of EnergySage's 11.64, which is reassuring. It also shows how little room there is. A 10 percent drop in production or a 10 percent price increase on the quote moves payback by more than a year. Systems that earn certificates do somewhat better; the certificate section below has the numbers.
A longer payback is not automatically a bad deal. A system that lasts 25 years and pays back in 12 returns its cost about twice. But the margin is thinner than in higher-rate states, so a quote that is $3,000 over the going rate matters more here. The solar ROI timeline walks through how panel degradation and rate changes bend that line.
What did regulators decide on Dominion net metering?
On April 30, 2026 the State Corporation Commission kept annual netting for new Dominion Energy Virginia solar customers and rejected the utility's request to cut the credit, according to pv magazine USA and the Southern Environmental Law Center. The ruling covers Dominion only. Appalachian Power customers fall under their own tariff.
What stayed the same: your solar output offsets your own use first, and extra energy carries forward within a 12-month period. Dominion had asked to move to 30-minute netting, and the Commission refused. It also rejected a proposed application fee of $100 to $750 by system size.
What changed, per pv magazine: new customers pay a $1 monthly administrative fee, and net excess generation at the end of the year is paid at the avoided-cost rate plus one cent per kWh. EnergySage prices that surplus at $0.05829 per kWh. The two sources describe the same rule from different ends, so check the figure on Dominion's current tariff sheet when you sign. Customers already on the old tariff may stay on it indefinitely, and Dominion has to file revised tariffs within 90 days of the order.
The practical limits are the same as before. EnergySage lists systems up to 25 kW, sizing up to 150 percent of the prior 12 months of use for Dominion customers, and a statewide cap of 6 percent of the prior year's peak load, with 1 percent reserved for low-income customers. The 6 percent cap is the point at which the Commission said it may revisit the rules.
How much does oversizing cost in Dominion territory?
Every kilowatt-hour above your annual use is worth about a third of what a kilowatt-hour you use is worth, so the extra panels rarely pay for themselves. Here is the worked example. A household uses 9,000 kWh a year. The 150 percent allowance lets it build a system producing 13,500 kWh.
| System sized to |
Production |
Surplus beyond use |
Value of that surplus |
| 100 percent of use |
9,000 kWh |
0 kWh |
$0 |
| 150 percent of use |
13,500 kWh |
4,500 kWh |
4,500 x $0.05829 = $262 a year |
The extra 3.6 kW of panels (4,500 kWh at 1,250 kWh per kW) costs roughly 3,600 W x $2.56 = $9,216. Earning $262 a year, it takes about 35 years to pay back, longer than the panels last. If those same 4,500 kWh were offset against a heat pump or an EV charger you actually own, they would be worth 4,500 x $0.1764 = $794 a year, and the extra panels pay back in under 12 years. The size that works is the one that matches use you will really have, not the allowance. Our EV home-solar guide shows how much a car adds to the load.
EnergySage notes that credits can be carried forward at the end of the cycle instead of being paid out, so a year with surplus followed by a year with a new load is not a total loss. It is still a poor reason to buy panels.